Soil-Cement Floor Slab

Replace a dust floor with a compacted, cement-stabilised earth slab that sweeps clean, resists damp and costs a fraction of a full concrete pour.

Workers screeding and floating a freshly poured floor slab level
Photo: U.S. Defense Visual Information Center · Public domain. Reference photo of a comparable build, not the exact plan below.
Estimated cost
$90 – $250 for a 20 m² room
Skill level
Intermediate
Time
2 days to lay, 7 days moist curing

Not yet verified

No confirmed build with photo proof has been submitted for this plan yet. Built it? Send photos and it earns the badge.

Tools

  • Hand tamper or plate compactor
  • Screed board and wooden float
  • Steel trowel
  • Wheelbarrow and shovels
  • Spirit level and screed rails

Short a tool or material? Builders below have often swapped something local in — read Local adaptations before you buy anything.

Materials

  • Sandy sub-soil, low clay, screened of stones over 20 mm
  • Cement at roughly 1 part to 10 – 12 of soil by volume
  • Clean water
  • Damp-proof plastic sheeting, 250 micron
  • Hardcore stone for the base layer

Dimensions & cut list

A stabilised soil-cement floor slab over 20 m² of an existing earth floor. These are the reference sizes from Appropedia / stabilised earth construction guides — scale them to what you have, but keep the ratios.

Slab thickness75 mm compactedLaid in one layer over a prepared hardcore base
Hardcore base100 mm of compacted rubble or coarse stone
Cement content8–10% by weight of dry soil
Soil gradingSandy soil, under 20% clay, no organic matter
Mix moistureOptimum by drop test — just damp enough to hold a ball
CompactionHand-rammed in strips, then screeded
CuringKept damp under plastic or sacking for 7 daysThis is the step people skip, and it is why floors dust up later
FinishSteel-trowelled, then sealed with linseed oil or a lime wash

Take this list to the yard

  • ≈ 8 bags for 20 m²Cement
  • 1.8 m³Screened sandy subsoil
  • 2 m³Hardcore stone
  • 25 m²Plastic sheet or sacking for curing
  • 1 setScreed board, ram and steel float
  • 4 litresLinseed oil for sealing

Step by step

Step 1 of 6

1

Excavate and lay hardcore

Strip organic soil, level, then compact 100 mm of hardcore. Any soft spots left now will show as cracks in six months.

Swipe or use arrow keys

Why mine failed

The ways this build usually goes wrong, and what fixes it.

  • Floor dusts up within months

    CauseNot cured, or too little cement

    FixKeep it damp under plastic or sacking for seven full days and use 8–10% cement. Curing is free and it is what makes the floor last.

  • Floor cracks in a pattern of squares

    CauseClayey soil shrinking

    FixUse a sandy soil with under 20% clay and no organic matter. Test a small panel before committing to the whole room.

  • Surface crumbles under foot traffic

    CauseMix too wet and poorly compacted

    FixMix to the drop test — just damp — and hand-ram in strips before screeding. A soupy mix always gives a weak surface.

  • Damp comes up through the floor

    CauseNo hardcore base or DPC

    FixLay 100 mm of compacted hardcore, and a polythene DPC under the slab where the ground stays wet.

Safety notes

  • Cement burns skin and eyes. Wear gloves and rinse splashes immediately.
  • Mixing dry cement raises silica dust — wear a mask and mix outdoors or with the doors open.
  • Do not walk on the slab for 24 hours or load it for a week.
  • Skip this floor in rooms that flood; a stabilised earth slab is water-resistant, not waterproof.

Source & attribution

This plan is our build-step write-up of work documented by Appropedia / stabilised earth construction guides. The original design and documentation belong to them — go read the source before you build.

Soil-cement

Local adaptations

What builders changed to make this work where they live.

  • No adaptations shared yet for this plan.